Phase 3
Petaling, SelangorMap (opens Google Maps in a new tab)
Handover
+23 months
Handover was pushed back 23 months, while only 44% of Selangor projects launched in 2018 were.
Schedule
The developer's sales permit for this project was cancelled.
Progress
Progress or contract dates haven't been reported.
Price
This project launched before 2021. Signed prices from then almost always match the asking price on record, so the discounts buyers got don't show.
Developer
Paid is the price in each buyer's signed SPA. Asking is the developer's listed price. Est. after discount is an estimate for units still for sale: the asking price less the discount buyers of that type typically got.
This project launched before 2021. Signed prices from then almost always match the asking price on record, so the discounts buyers got don't show.
No unit prices are on record for this project.
Data as of 12 Sept 2026. Prices and availability can change; confirm with the developer before you commit.
3 projects on record. Handover was extended on 3 of 3.