Phase 1
Seremban, Negeri SembilanMap (opens Google Maps in a new tab)
Handover
+5 months
Handover was pushed back 5 months, while only 22% of Negeri Sembilan projects launched in 2021 were.
Discounts
Few discounts
Only 14% of buyers signed below asking, against 46% across Negeri Sembilan.
Schedule
Completed (CCC).
Progress
Construction is complete.
Price
Only 14% of buyers signed below the asking price.
Developer
Paid is the price in each buyer's signed SPA. Asking is the developer's listed price. Est. after discount is an estimate for units still for sale: the asking price less the discount buyers of that type typically got.
Asking vs paid
Some buyers got 34% off the asking price
15 of 109 buyers signed below asking, typically saving about RM 260,060.
From the price in each signed SPA. Cashback, rebates and free extras given outside the SPA aren't included, so some buyers paid less still.
Completed homes within 8 km, nearest first.
| Development | Median price | Median psf | Distance |
|---|---|---|---|
| TAMAN BUKIT KRISTAL | RM 285,000 | RM 325 psf | 3.4 km · 49 sales |
Each unit's asking price and sale status, with what sold units signed at and an estimated price for units for sale.
See every unit with Agents
The Agents plan shows all 110 units: which are sold, what each buyer signed for, and the estimated price of the units still for sale.
See the Agents planData as of 12 Sept 2026. Prices and availability can change; confirm with the developer before you commit.
43 projects on record. Handover was extended on 6 of 11.
Terrace house
0 of 110 units are Bumiputera lots