Discounts
Few discounts
Only 1% of buyers signed below asking, against 64% across Kuala Lumpur.
Handover
+18 months
Handover was pushed back 18 months, like most Kuala Lumpur projects launched in 2025 (88%).
Schedule
The developer was approved to hand over later than first promised in the sale and purchase agreement.
Progress
27% built, with 25% of the promised build time used.
Price
Only 1% of open-lot buyers signed below the asking price.
Paid is the price in each buyer's signed SPA. Asking is the developer's listed price. Est. after discount is an estimate for units still for sale: the asking price less the discount buyers of that type typically got.
Asking vs paid
Some buyers got 16% off the asking price
2 of 236 open-lot buyers signed below asking, typically saving about RM 114,438.
Bumiputera lots: 43% signed below asking, typically 5% off, which includes the Bumiputera discount.
From the price in each signed SPA. Cashback, rebates and free extras given outside the SPA aren't included, so some buyers paid less still.
Each unit's asking price and sale status, with what sold units signed at and an estimated price for units for sale.
See every unit with Agents
The Agents plan shows all 794 units: which are sold, what each buyer signed for, and the estimated price of the units still for sale.
See the Agents planData as of 11 Sept 2026. Prices and availability can change; confirm with the developer before you commit.
Developer
Developers often set up a separate company per project, so check the parent group's record too.
Apartment / condominium
400 of 794 units are Bumiputera lots