Phase 3
Handover
+12 months
Handover was pushed back 12 months, while only 12% of Perak projects launched in 2025 were.
Discounts
Full price
All 23 buyers signed at the asking price, while 38% of Perak sales since 2021 were below asking.
Schedule
The developer was approved to hand over later than first promised in the sale and purchase agreement.
Progress
43% built, with 37% of the promised build time used.
Price
All 23 open-lot buyers signed at the asking price.
Paid is the price in each buyer's signed SPA. Asking is the developer's listed price. Est. after discount is an estimate for units still for sale: the asking price less the discount buyers of that type typically got.
Asking vs paid
Every buyer paid the asking price
All 23 open-lot buyers signed at the asking price.
Bumiputera lots: 38% signed below asking, typically 7% off, which includes the Bumiputera discount.
From the price in each signed SPA. Cashback, rebates and free extras given outside the SPA aren't included, so some buyers paid less still.
Each unit's asking price and sale status, with what sold units signed at and an estimated price for units for sale.
See every unit with Agents
The Agents plan shows all 58 units: which are sold, what each buyer signed for, and the estimated price of the units still for sale.
See the Agents planData as of 11 Sept 2026. Prices and availability can change; confirm with the developer before you commit.
Developer
3 projects on record. Handover was extended on 1 of 3.
Unclassified
Semi-detached house
22 of 58 units are Bumiputera lots