Arkibena Construction Sdn. Bhd.
Cameron Highlands, PahangMap (opens Google Maps in a new tab)
Handover
+6 months
Handover was pushed back 6 months, while only 10% of Pahang projects launched in 2026 were.
Discounts
Few discounts
Only 4% of buyers signed below asking, against 37% across Pahang.
Schedule
The developer was approved to hand over later than first promised in the sale and purchase agreement.
Progress
10% built, with 9% of the promised build time used.
Price
Only 4% of buyers signed below the asking price.
Developer
Paid is the price in each buyer's signed SPA. Asking is the developer's listed price. Est. after discount is an estimate for units still for sale: the asking price less the discount buyers of that type typically got.
Asking vs paid
Some buyers got 10% off the asking price
3 of 74 buyers signed below asking, typically saving about RM 20,000.
From the price in each signed SPA. Cashback, rebates and free extras given outside the SPA aren't included, so some buyers paid less still.
Each unit's asking price and sale status, with what sold units signed at and an estimated price for units for sale.
See every unit with Agents
The Agents plan shows all 576 units: which are sold, what each buyer signed for, and the estimated price of the units still for sale.
See the Agents planData as of 11 Sept 2026. Prices and availability can change; confirm with the developer before you commit.
Developers often set up a separate company per project, so check the parent group's record too.
Apartment / condominium
0 of 576 units are Bumiputera lots