Sales
52% sold
52% sold since its 2020 launch, slower than most Kuala Lumpur projects launched that year.
Handover
+36 months
Handover was pushed back 36 months, like most Kuala Lumpur projects launched in 2020 (91%).
Schedule
The developer was approved to hand over later than first promised in the sale and purchase agreement.
Progress
93% built, with 97% of the promised build time used.
Price
This project launched before 2021. Signed prices from then almost always match the asking price on record, so the discounts buyers got don't show.
Developer
Paid is the price in each buyer's signed SPA. Asking is the developer's listed price. Est. after discount is an estimate for units still for sale: the asking price less the discount buyers of that type typically got.
This project launched before 2021. Signed prices from then almost always match the asking price on record, so the discounts buyers got don't show.
SOHO
1 of 506 units are Bumiputera lots
Each unit's asking price and sale status, with what sold units signed at and an estimated price for units for sale.
See every unit with Agents
The Agents plan shows all 506 units: which are sold, what each buyer signed for, and the estimated price of the units still for sale.
See the Agents planData as of 11 Sept 2026. Prices and availability can change; confirm with the developer before you commit.
Developers often set up a separate company per project, so check the parent group's record too.