Phase 2
Discounts
9% off
Nearly all buyers got about 9% off the asking price, less than most in Selangor.
Bumiputera lots
18% off
Bumiputera lots typically got 18% off, against 9% for open lots.
Schedule
Construction is listed as progressing normally, with no change to the handover date.
Progress
3% built, with 7% of the promised build time used.
Price
100% of open-lot buyers signed below the asking price. Treat it as a starting point and negotiate.
Paid is the price in each buyer's signed SPA. Asking is the developer's listed price. Est. after discount is an estimate for units still for sale: the asking price less the discount buyers of that type typically got.
Asking vs paid
Nearly all buyers got 9% off the asking price
17 of 17 open-lot buyers signed below asking, typically saving about RM 34,010. 1 in 10 of them got 13% or more off.
Bumiputera lots: 100% signed below asking, typically 18% off, which includes the Bumiputera discount.
From the price in each signed SPA. Cashback, rebates and free extras given outside the SPA aren't included, so some buyers paid less still.
Each unit's asking price and sale status, with what sold units signed at and an estimated price for units for sale.
See every unit with Agents
The Agents plan shows all 364 units: which are sold, what each buyer signed for, and the estimated price of the units still for sale.
See the Agents planData as of 12 Sept 2026. Prices and availability can change; confirm with the developer before you commit.
Developer
3 projects on record. Handover was extended on 2 of 3.
Serviced apartment
15 of 364 units are Bumiputera lots